Farcaster v3 will make the network permissionless. The migration will take 2-4 weeks to complete and by the end of it:
<aside> đź’ˇ Many things are changing
The tables in each phase below give you a sense for when and how your app might be affected, while the details below them tell you how to remedy the issues.
</aside>
Phase | Start Date |
---|---|
1. Preparation | 2023-8-17 |
2. Migration | 2023-8-29 |
3. Trusted Signups | 2023-8-30 |
4. Permissionless Signups | 2023-9-1 to 2023-11-1 |
<aside> ⚠️ Timelines are volatile
It’s possible that we run into unforeseen issues that require remigration or other significant work. That’s why permissionless signups has such a broad range. We expect to dial things in as we work through the migration.
</aside>
Users | No impact |
---|---|
Warpcast API | No impact |
Hubble | - Install Hubble v1.5 on 23.8.2023 to prep for Phase 2 |
Hubble APIs | - Getting usernames requires a new API |
Contracts | No impact |